Project 16CG0119
DPWH infrastructure contract
Contract ID:
16CG0119
Fingerprint:
5043108dca35c7…03cd9078e3 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 4, 2016 (10 yrs 3 mo ago) · Target/actual end Oct 2, 2016
Description:
CONST./MAINT. OF FLOOD MITIGATION STRUCTURE & DRAINAGE SYSTEM - REHAB. OF CHECKGATE AT BEBE ANAC, PUROC BULUGO, MASANTOL, PAMPANGA
Category:
Flood Control and Drainage
Implementing office:
DPWH Pampanga 1st DEO · Region III
Contractor:
MARVERIC BUILDERS · DPWH contractor code 17102
Contract amount:
₱3,605,257.91 (₱3.6M)
Funding source:
Regular Infra - GAA 2016 MFO-2
Budget year:
2016
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CG0117 | Jun 11, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD WITH SLOPE PROTECTION WORKS, BARANGAY CAMBASI (CENTRO), MASANTOL, PAMPANGA | Completed | ₱56.3M |
| 25CG0126 | Jun 11, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD WITH SLOPE PROTECTION WORKS, BARANGAY SAGRADA - BARANGAY NIGUI, MASANTOL, PAMPANGA | Completed | ₱93.8M |
| 25CG0127 | Jun 11, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD WITH SLOPE PROTECTION WORKS, BARANGAY BAGANG - BARANGAY BALIBAGO, MASANTOL, PAMPANGA | Completed | ₱93.9M |
| 25CG0086 | Jun 10, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION (COMPLETION) OF ROAD WITH SLOPE PROTECTION WORKS, BARANGAY ANAC - STA. LUCIA WAKAS, MASANTOL, PA | Completed | ₱37.5M |
| 25CG0170 | Jun 5, 2025 | CONCRETING OF SITIO MINDANAO, BRGY. ESTEBAN FARM-TO-MARKET ROAD, BRGY. ESTEBAN, MACABEBE, PAMPANGA | Completed | ₱14.1M |
| 25CG0014 | May 22, 2025 | FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF ERODED PAMPANGA RIVER BANK AT BARANGAY BEBE ANAC, MASANTOL, PAMPANGA | On-Going | ₱140.4M |
| 25CG0023 | May 22, 2025 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS) - CONSTRUCTION OF BY-PASS ROAD AND BRIDGE (SAN ESTEBAN) MACABEBE - MALAULI (PHASE IV), MASANTOL, PAMPAN | Completed | ₱44.0M |
| 25CG0111 | Apr 2, 2025 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REPAIR / REHABILITATION OF ERODED PAMPANGA RIVER BANK (LANDSLIDE SECTION) (PHASE 1) | Terminated | ₱0 |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.