Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 16CG0182

DPWH infrastructure contract
Contract ID:
16CG0182
Fingerprint:
4e2535e655c6cf…97261951e9 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 26, 2016 (9 yrs 10 mo ago) · Target/actual end Feb 23, 2017
Description:
LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION OF CUAYAN BUGTONG COVERED COURT, CANDABA, PAMPANGA 4TH LD
Category:
Buildings and Facilities
Implementing office:
DPWH Pampanga 1st DEO · Region III
Contractor:
ST. LOUISE PRIME BUILDERS & DEVELOPMENT CORP. · DPWH contractor code 39033
Contract amount:
₱1,920,565.32 (₱1.9M)
Funding source:
Regular Infra - GAA 2016 Locally Funded Projects
Budget year:
2016

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.