Project 16CJ0095
DPWH infrastructure contract
Contract ID:
16CJ0095
Fingerprint:
e028fa266e527d…df0cca89dc Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 17, 2016 (10 yrs 3 mo ago) · Target/actual end Feb 1, 2017
Description:
REPAIR/REHABILITATION/IMPROVEMENT OF SLOPE PROTECTION ALONG TARLAC RIVER CONTROL, TIBAG SECTION, TAR
Category:
Flood Control and Drainage
Implementing office:
DPWH Tarlac DEO · Region III
Contractor:
NORTHERN BUILDERS · DPWH contractor code 8789
Location:
Contract amount:
₱36,629,735.82 (₱36.6M)
Funding source:
Regular Infra - GAA 2016 Locally Funded Projects
Budget year:
2016
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 4d16961af993… | Jul 28, 2016 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - TARLAC DEO | ₱36,629,735.82 |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.