FY2026 GAA: ₱6.79T
PisoScan

Project 16CK0118

DPWH infrastructure contract
Contract ID:
16CK0118
Fingerprint:
26db0bae0176ec…4c5afc9f1a Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 14, 2017 (9 yrs 9 mo ago) · Target/actual end Jun 25, 2017
Description:
REHAB./IMPT. OF EXISTING DIKE ALONG LUCUNG RIVER (BRGY. CULATINGAN SECTION, LEFT BANK), CONC., TAR.
Category:
Flood Control and Drainage
Implementing office:
DPWH Tarlac 2nd DEO · Region III
Contractor:
B.K. SY TU CONSTRUCTION · DPWH contractor code 12655
Contract amount:
₱21,848,776.51 (₱21.8M)
Funding source:
Regular Infra - GAA 2017 MFO-2
Budget year:
2017

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
51b9c29acbb2…Jan 27, 2017DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - TARLAC 2ND-DEO₱21,848,776.51