Project 16CK0189
DPWH infrastructure contract
Contract ID:
16CK0189
Fingerprint:
c7f8f7742370e9…329129cd94 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 23, 2017 (9 yrs 8 mo ago) · Target/actual end Oct 9, 2017
Description:
ASSETS PRESERV. OF NATL RDS-REHAB/RECONST OF NATL RDS W/ SLIPS, SLOPE COLLAPSE & LAND SLIDE ALONG
Category:
Roads
Implementing office:
DPWH Tarlac 2nd DEO · Region III
Contractor:
R.R. RICAFORT CONSTRUCTION AND SUPPLIES · DPWH contractor code 14402
Contract amount:
₱32,351,006.95 (₱32.4M)
Funding source:
Regular Infra - GAA 2017 MFO-1
Budget year:
2017
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 05607234584c… | Feb 7, 2017 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - TARLAC 2ND-DEO | ₱32,345,939.85 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CK0082 | Jun 13, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG THE BANKS OF RIO CHICO RIVER IN BARANGAY LOMBOY (PHASE VII), LA PAZ, TARLAC | Completed | ₱94.7M |
| 25CK0119 | May 20, 2025 | CONSTRUCTION OF SCHOOL BUILDING, LAPURISIMA INTEGRATED SCHOOL, LA PAZ, TARLAC | Completed | ₱9.7M |
| 25CK0089 | Apr 3, 2025 | REHABILITATION OF ROAD, BARANGAY DUMARAIS - BALANOY, PHASE 1, LA PAZ, TARLAC | Completed | ₱96.5M |
| 25CK0118 | Apr 3, 2025 | REHABILITATION OF ROAD AT BARANGAY SAN ROQUE, LA PAZ, TARLAC | Completed | ₱49.0M |
| 25CK0005 | Mar 25, 2025 | NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - TERTIARY ROADS ALONG VICTORIA - LA PAZ ROAD, K0135 + 075.00 - K0135 + 500.00, LA PAZ, TARLAC | Completed | ₱18.8M |
| 25CK0007 | Mar 25, 2025 | ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS ALONG VICTORIA - LA PAZ ROAD, LA PAZ, TARLAC | On-Going | ₱48.0M |
| 25CK0013 | Mar 25, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (PHASE I), LA PAZ, TARLAC | On-Going | ₱69.8M |
| 25CK0014 | Mar 25, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (PHASE II), LA PAZ, TARLAC | On-Going | ₱72.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.