Project 16DF0112

DPWH infrastructure contract
Contract ID:
16DF0112
Fingerprint:
5d8f17234f0984…89a17dea61 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 31, 2016 (10 yrs 5 mo ago) · Target/actual end Dec 26, 2016
Description:
CONSTRUCTION OF 4STY 16CL SCHOOL BUILDING AT AGUSTIN ABADILLA ES, ROSARIO
Category:
Buildings and Facilities
Implementing office:
DPWH Cavite 1st DEO · Region IV-A
Contractor:
R.D. MANDANAS CONSTRUCTION · DPWH contractor code 32114
Contract amount:
₱25,969,562.77 (₱26.0M)
Funding source:
Outside Infra - GAA 2016 DepED BEFF
Budget year:
2016

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
633ae8844db9…May 16, 2016DPWH-CAVITE I DISTRICT ENGINEERING OFFICE₱25,969,562.77

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25DF0165Jun 9, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIESCONSTRUCTION OF REVETMENT ALONG MALIMANGO RIVER, BRGY. BAGBAG I, ROSARIO, CAVITE (PHASOn-Going₱48.0M
25DF0037Mar 20, 2025ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM ASSET PRESERVATION PROGRAM REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS NOVELETA-NAIC-TAGAYTAY RD. - K0031 + 073 - K0031 + 561Completed₱24.8M
25DF0100Mar 20, 2025ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMBRIDGE PROGRAMREPLACEMENT OF PERMANENT WEAK BRIDGESMALIMANGO BR. (B02897LZ) ALONG NOVELETA-NAIC-TAGAYTAY RD (COMPLETION)On-Going₱5.1M
24DF0242May 15, 2024CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICESCONSTRUCTION (COMPLETION) OF ROSARIO GYMNASIUM, ROSARIO, CAVITEOn-Going₱147.1M
24DF0211Apr 25, 2024CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICESCONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY BAGBAG II, ROSARIO, CVITECompleted₱4.9M
24DF0142Mar 20, 2024ORGANIZATIONAL OUTCOME 1 :ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMBRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGESMALIMANGO BR. (B02897LZ) ALONG NOVELETA-NAIC-TAGAYTAY RD. (PHASE II)On-Going₱4.8M
24DF0012Feb 27, 2024'ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM ASSET PRESERVATION PROGRAM REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS NOVELETA-NAIC-TAGAYTAY RD - K0029+260 - K0029+600 'On-Going₱10.9M
24DF0006Feb 14, 2024CONVERGENCE AND SPECIAL SUPPORT PROGBASIC INFRASTRUCTURE PROG (BIP)BIP - ACCESS RD AND/OR BRIDGES FROM THE NATIONAL RD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BLDGS./FACILITIES CONST OF DRAINAGE SYSTEM (CANAL LINING) AT BRGY.BAGBAG II ROSARIO,(PHASE II)Completed₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.