Project 16DN0032
DPWH infrastructure contract
Contract ID:
16DN0032
Fingerprint:
498007e3385347…b7987c5f32 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 23, 2016 (10 yrs 7 mo ago) · Target/actual end Jul 20, 2016
Description:
NETWORK DEVELOPMENT OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE TERTIARY ROADS, IMELDA AVE., K0020+800-K0021+638, CAINTA, RIZAL
Category:
Flood Control/Hydraulics/Drainage, Roads: Rehabilitation - PCCP
Implementing office:
DPWH Rizal 1st DEO · Region IV-A
Contractor:
HEXAMINDZ CORPORATION (FORMERLY:KILUSANG MAGKAIBIG · DPWH contractor code 31666
Contract amount:
₱14,905,382.58 (₱14.9M)
Funding source:
Regular Infra - Flood Control/Hydraulics/Drainage, Roads: Rehabilitation - PCCP
Budget year:
2016
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26OB0090 | Jun 22, 2026 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - PASIG BLVD C5 FLYOVER (B01876LZ) ALONG C-5 ROAD | On-Going | ₱74.3M |
| 26OB0088 | May 21, 2026 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - C5/ORTIGAS FLYOVER (B03319LZ) ALONG C5- ORTIGAS FLYOVER, PHASE II | On-Going | ₱97.8M |
| 26OB0089 | May 21, 2026 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - ORTIGAS BR. (B01868LZ) ALONG MANILA EAST RD (ROSARIO-CAINTA RD) | On-Going | ₱89.9M |
| 26OB0091 | May 12, 2026 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - C5/ORTIGAS FLYOVER (B03318LZ) ALONG C5- ORTIGAS FLYOVER, PHASE II | On-Going | ₱25.4M |
| 26OB0092 | May 12, 2026 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - DAAN PASIG BR. (B01874LZ) ALONG AMANG RODRIGUEZ RD | On-Going | ₱23.8M |
| 25OB0461 | Jun 20, 2025 | CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM IN PUBLIC FACILITIES IN METRO MANILA 1ST DISTRICT ENGINEERING OFFICE | Completed | ₱2.6M |
| 25OG0038 | May 23, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MARIKINA RIVER, PHASE 4, BARANGAY BAGUMBAYAN, QUEZON CITY | On-Going | ₱48.0M |
| 25OG0039 | May 23, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MARIKINA RIVER, PHASE 5, BARANGAY BAGUMBAYAN, QUEZON CITY | On-Going | ₱48.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.