Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 16EH0127

DPWH infrastructure contract
Contract ID:
16EH0127
Fingerprint:
2dfffda69946f1…c2a0fa9b9b Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 24, 2016 (10 yrs 2 mo ago) · Target/actual end Dec 22, 2016
Description:
ROAD UPGRADING (UNPAVED TO PAVED) OF ODIONGAN - EAST WEST ROAD, K0007 + 682.31 - K0007 + 798.59 (AS PER SURVEY), K0007 + 660.00 - K0007 + 740.00 (AS PER RBIA), K0008 + 237.00 - K0008 + 295.00 (AS PER SURVEY & RBIA), ODIONGAN, ROMBLON
Category:
GAA 2016 MFO-1
Implementing office:
DPWH Romblon DEO · MIMAROPA Region
Contractor:
TWIN DRAGON CONSTRUCTION · DPWH contractor code 11392
Contract amount:
₱5,400,000.00 (₱5.4M)
Funding source:
Regular Infra - GAA 2016 MFO-1
Budget year:
2016

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
d1d79da4585b…Aug 3, 2016DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ROMBLON DEO₱5,134,722.81

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26EH0001Jul 9, 2026CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BATIANO, ODIONGAN, ROMBLON (12.4201306 ° N, 121.989187 ° E), ODIONGAN, ROMBLONOn-Going₱8.8M
25EH0061Jul 28, 2025CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG DAPAWAN-TORREL RD, K0002+046 + K0002+691.50 AS PER ACTUAL & RBIA, TABLAS ISLAND, ROMBLONOn-Going₱12.6M
25EH0146Jul 28, 2025CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG TABLAS CIRCUMFERENTIAL RD, K0127+760 - K0127+898.50, K0127+902.90 - K0128+022 AS PER RBIA, K0127+760 - K0127+898.50, K0127+902.90 - K0128+020 AS PER ACTUAL, TABLAS ISLAND, ROMBLONCompleted₱4.9M
25EH0168Jul 28, 2025COMPLETION OF MULTI-PURPOSE BUILDING (UKR) AT BARANGAY TABIN-DAGAT, ODIONGAN, ROMBLONCompleted₱2.0M
25EH0060Jul 25, 2025CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG LOOC (COGON TULAY)-ODIONGAN RD, K0103+315.00 - K0103+563.00 (FIRST SECTION), K0123+300.00 - K0123+402.00 (SECOND SECTION), TABLAS ISLAND, ROMBLONOn-Going₱4.4M
25EH0130Jul 11, 2025CONSTRUCTION OF TUGUIS WATER IMPOUNDING PROJECT, ODIONGAN, ROMBLONOn-Going₱48.0M
25EH0110Jul 10, 2025CONSTRUCTION OF REVETMENT STRUCTURE ALONG PATO-O RIVER, ODIONGAN, ROMBLONOn-Going₱139.7M
25EH0111Jul 10, 2025CONSTRUCTION OF REVETMENT STRUCTURE ALONG PATO-O RIVER (PHASE 2), ODIONGAN, ROMBLONOn-Going₱139.8M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.