Project 16F00066
DPWH infrastructure contract
Contract ID:
16F00066
Fingerprint:
f15fb61eab6f4c…ae908c7728 Verified
Status:
Completed
Physical progress:
99.8%
Timeline:
Start Dec 1, 2016 (9 yrs 11 mo ago) · Target/actual end Oct 22, 2017
Description:
REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, LAGONOY-PRESENTACION ROAD, K0505+018 TO K0520+640 WITH EXCEPTIONS, CAMARINES SUR
Category:
Roads
Implementing office:
DPWH Region V · Region V
Contractor:
G.C.I. CONSTRUCTION AND DEV'T. CORP. · DPWH contractor code 11346
Contract amount:
₱93,843,398.97 (₱93.8M)
Funding source:
Regular Infra - GAA 2016 MFO-1
Budget year:
2016
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25FG0099 | Jul 8, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, LAGONOY, CAMARINES SUR | On-Going | ₱47.5M |
| 25FG0068 | Jun 26, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (DRAINAGE SYSTEM) BARANGAY SAN RAFAEL TO SAN ISIDRO SUR HIGHWAY), LAGONOY, CAMARINES SUR | On-Going | ₱4.7M |
| 25FG0051 | Jun 25, 2025 | CONSTRUCTION OF ROAD WITH DRAINAGE ALONG TIGAON-GOA-SAN JOSE-LAGONOY-GUIJALO VIA SAN VICENTE ROAD, BARANGAY SAN RAFAEL SECTIONLAGONOY, CAMARINES SUR | On-Going | ₱9.4M |
| 25FG0030 | Apr 4, 2025 | CONSTRUCTION OF MISSING LINKS/NEW ROADS, LALUD-GARCHITORENA ROAD (DEL CARMEN SECTION), CAMARINES SUR, LAGONOY, CAMARINES SUR | On-Going | ₱65.4M |
| 25FG0029 | Mar 31, 2025 | CONSTRUCTION OF DRAINAGE CANAL AT CRIS, LAGONOY, CAMARINES SUR | On-Going | ₱9.6M |
| 25FG0032 | Mar 31, 2025 | CONSTRUCTION OF DRAINAGE CANAL AT CRIS, BARANGAY LOHO, LAGONOY, CAMARINES SUR | On-Going | ₱14.4M |
| 25F00127 | Mar 12, 2025 | ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, LAGO | On-Going | ₱159.0M |
| 25F00128 | Mar 12, 2025 | ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, LAGO | On-Going | ₱154.3M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.