Project 16G00091
DPWH infrastructure contract
Contract ID:
16G00091
Fingerprint:
874a6c86360d52…1ac294dbd0 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 16, 2016 (10 yrs 3 mo ago) · Target/actual end Apr 25, 2019
Description:
IMPVT./WIDENING INCLUDING RROW OF ILOILO - CAPIZ ROAD (OLD ROUTE), K0021+294 - K0023+059, K0029+900
Category:
Roads
Implementing office:
DPWH Region VI · Region VI
Contractor:
IBC INTERNATIONAL BUILDERS CORPORATION · DPWH contractor code 8576
Contract amount:
₱119,725,351.63 (₱119.7M)
Funding source:
Regular Infra - GAA 2016 MFO-1
Budget year:
2016
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 7c1fe266d6b0… | Jun 6, 2016 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION VI | ₱123,699,999.99 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26GR0036 | Jul 23, 2026 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - CABATUAN BYPASS RD - (S00565PN) CHAINAGE 003 - CHAINAGE 700 | On-Going | ₱28.5M |
| 25GG0056 | Jul 4, 2025 | CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY AMERANG, CABATUAN, ILOILO | Completed | ₱2.9M |
| 25GG0057 | Jul 4, 2025 | CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY LAG-AN, CABATUAN, ILOILO | Completed | ₱3.4M |
| 25GG0102 | Jul 4, 2025 | PREVENTIVE MAINTENANCE OF ROAD: CONCRETE REBLOCKING - CABATUAN BYPASS ROAD - CHAINAGE 929 - CHAINAGE 3094 | Completed | ₱9.8M |
| 25GG0153 | Jul 4, 2025 | CONSTRUCTION OF MULTI - PURPOSE BUILDING, BARANGAY PAGOTPOT, CABATUAN, ILOILO | Completed | ₱9.8M |
| 25GG0101 | Jun 6, 2025 | CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING OF BARANGAY SULANGA, CABATUAN, ILOILO | Completed | ₱2.4M |
| 25GI0078 | Jun 4, 2025 | CONSTRUCTION OF SCHOOL BUILDING, TUGAS ELEMENTARY SCHOOL, BARANGAY TUGAS, STA. BARBARA, ILOILO | Completed | ₱9.9M |
| 25GI0069 | Jun 3, 2025 | CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE, BARANGAY MANASA, ALIMODIAN, ILOILO (SITE 3) | Completed | ₱96.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.