Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 16G00125

DPWH infrastructure contract
Contract ID:
16G00125
Fingerprint:
44abfc5a3ca6ce…68fac23dec Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 18, 2016 (10 yrs 2 mo ago) · Target/actual end Jun 2, 2017
Description:
IMPROVEMENT/WIDENING OF ILOILO EAST COAST - CAPIZ ROAD, K0175+844 - K0176+528, K0176+528 - K0177+169
Category:
Roads
Implementing office:
DPWH Region VI · Region VI
Contractor:
IBC INTERNATIONAL BUILDERS CORPORATION · DPWH contractor code 8576
Contract amount:
₱81,149,515.51 (₱81.1M)
Funding source:
Regular Infra - GAA 2016 MFO-1
Budget year:
2016

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
a0b4cce85e2b…Aug 3, 2016DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION VI₱77,091,251.38

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GH0158Jun 13, 2025CONSTRUCTION OF MUNICIPAL HALL BUILDING AT BARANGAY POBLACION SUR, BALASAN, ILOILOCompleted₱4.9M
25GH0168May 27, 2025CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY BATUAN, BALASAN, ILOILOOn-Going₱3.0M
25GH0150May 26, 2025CONSTRUCTION OF RIVER WALL SLOPE PROTECTION FOR BRGY. MAYA AND BRGY. POBLACION SUR BOUNDARY, BRGY. DOLORES, AND BRGY. QUIASAN, BALASAN, ILOILOOn-Going₱4.9M
25GH0002Mar 26, 2025CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY TINGUIAN, BALASAN, ILOILOCompleted₱2.0M
25GH0010Mar 26, 2025CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY MAMHUT NORTE, BALASAN, ILOILOCompleted₱3.0M
25GH0116Mar 25, 2025CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY PANI- AN, BALASAN, ILOILOOn-Going₱3.0M
25GH0094Mar 24, 2025CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY SALVACION, BALASAN, ILOILOOn-Going₱2.9M
25GH0061Feb 19, 2025PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - ILOILO EAST COAST CAPIZ RD - K0177 + 158 - K0177 + 979Completed₱34.3M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.