Project 16GB0001
DPWH infrastructure contract
Contract ID:
16GB0001
Fingerprint:
86396a5d19e62e…42287df665 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 23, 2016 (10 yrs 7 mo ago) · Target/actual end Mar 31, 2017
Description:
CONSTRUCTION OF REVETMENT AT SIBALOM RIVER ALONG SAN REMIGIO-BUGO ROAD, ANTIQUE, SAN REMIGIO, ANTIQU
Category:
Flood Control and Drainage
Implementing office:
DPWH Antique DEO · Region VI
Contractor:
F. GURREA CONSTRUCTION, INCORPORATED · DPWH contractor code 6995
Location:
Contract amount:
₱24,248,631.75 (₱24.2M)
Funding source:
Regular Infra - GAA 2016 MFO-2
Budget year:
2016