Project 16GB0168
DPWH infrastructure contract
Contract ID:
16GB0168
Fingerprint:
73dd6222dd712e…e59213a9da Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 25, 2017 (9 yrs 5 mo ago) · Target/actual end Dec 15, 2017
Description:
CONSTRUCTION OF REVETMENT AT SIBALOM RIVER ALONG ODIONG-SIBALOM-SAN REMIGIO-LEON ROAD, SIBALOM, ANTI
Category:
GAA 2017 MFO-2
Implementing office:
DPWH Antique DEO · Region VI
Contractor:
LEGACY CONSTRUCTION CORPORATION (FORMERLY: LEGACY CONSTRUCTION) (22465) / SETTLERS BUILDER · DPWH contractor code 21643
Location:
Contract amount:
₱37,173,360.00 (₱37.2M)
Funding source:
Regular Infra - GAA 2017 MFO-2
Budget year:
2017
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.