Project 16GD0078
DPWH infrastructure contract
Contract ID:
16GD0078
Fingerprint:
5399bc7842105e…740e5eadec Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 12, 2017 (9 yrs 9 mo ago) · Target/actual end Nov 2, 2017
Description:
CONST/MAINT OF FLD MIT STRCT & DRAIN SYS, CONST/REHAB OF CADIO FLD CTRL ALONG PANAY RIVER, CAPIZ
Category:
Flood Control and Drainage
Implementing office:
DPWH Capiz 1st DEO · Region VI
Contractor:
ROMA CONSTRUCTION & DEVELOPMENT CORPORATION · DPWH contractor code 6514
Location:
Contract amount:
₱32,396,828.26 (₱32.4M)
Funding source:
Regular Infra - GAA 2017 MFO-2
Budget year:
2017
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.