Project 16GI0003
DPWH infrastructure contract
Contract ID:
16GI0003
Fingerprint:
a86715f240eb9b…fcb166cce9 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 10, 2016 (10 yrs 8 mo ago) · Target/actual end May 8, 2016
Description:
CONST. AND MAINT. OF VARIOUS BRIDGES ALONG NATIONAL ROAD,RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES, A.PENAFLORIDA DEZA BR. (B00468PN), ILOILO EAST COAST COAST-CAPIZ RD B. BOLO BR (B00170PN), C. ILOG ILOG BR (B00172PN) GUIMBAL-IGBARAS-TUBUNGAN-LEON
Category:
Bridges
Implementing office:
DPWH Iloilo 4th DEO · Region VI
Contractor:
TOPMOST DEVELOPMENT & MKTG. CORP. · DPWH contractor code 13361
Contract amount:
₱10,006,118.28 (₱10.0M)
Funding source:
Regular Infra - GAA 2016 MFO-1
Budget year:
2016
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GI0068 | Sep 9, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, LEON, ILOILO | On-Going | ₱9.8M |
| 25GI0081 | Jul 11, 2025 | CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM | Completed | ₱2.6M |
| 25GI0059 | Jun 4, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BINOLBOG, LEON, ILOILO | Completed | ₱4.9M |
| 25GI0056 | May 20, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TUOG, LEON, ILOILO | Completed | ₱4.9M |
| 25GI0057 | May 20, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY IGCADIOS, LEON, ILOILO | On-Going | ₱4.9M |
| 25GI0058 | May 20, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TACUYONG SUR, LEON, ILOILO | Completed | ₱4.9M |
| 25GI0036 | Mar 25, 2025 | CONSTRUCTION OF SIBALOM FLOOD CONTROL STRUCTURE, SIBALOM RIVER, BARANGAY NAGBANGI, LEON, ILOILO | Completed | ₱29.1M |
| 25GI0039 | Mar 25, 2025 | CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - JCT BANCAL-LEON-ANTIQUE BDRY RD - K0042 + 435 - K0042 + 480 | Completed | ₱22.3M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.