Project 16IF0077
DPWH infrastructure contract
Contract ID:
16IF0077
Fingerprint:
6b6ba348b40740…463bb1f8d8 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 3, 2016 (10 yrs 1 mo ago) · Target/actual end Sep 29, 2018
Description:
WIDENING OF PERMANENT BRIDGE, ANILAO BRIDGE (B00618LT) ALONG PALO - CARIGARA - ORMOC ROAD, ORMOC CITY
Category:
Bridges
Implementing office:
DPWH Region VIII · Region VIII
Contractor:
LEDA CONSTRUCTION INCORPORATED · DPWH contractor code 12229
Location:
Not stated in the source
Contract amount:
₱55,759,992.02 (₱55.8M)
Funding source:
Regular Infra - GAA 2016 MFO-1
Budget year:
2016
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 0b8eba693d19… | Aug 24, 2016 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LEYTE 4TH DEO | ₱55,759,992.02 |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.