Project 16J00122
DPWH infrastructure contract
Hashed input (canonical JSON of the source row)
["dpwh","16J00122","IMPROVEMENT/UPGRADING/REHABILITATION OF JUNCTION TIMBANGAN- ROMANDIER ROAD AND ROMANDIER-CAMP ANDRES ROAD, TALIPAO, SULU, 1ST DEO (CLUSTERED), SECT. 1: STA.18+180.00 TO STA.18+839.71 (NET LENGTH: 659.71 LN.M.), SECT. 2: STA.19+501.00 TO STA.20+080.00 (NET","Roads","Completed",92086642.74,0,100,"Region IX","Region IX","M. ABUBAKAR CONST. AND ENGINEERING, INC. (36365)","2016-09-27","2017-01-09",2016,"Regular Infra - GAA 2016 Locally Funded Projects",6.00361,120.99539,"906601000","906600000"]
SHA-256
c3019d9a2c023291115c19f821fbde65c50b65ab22caeff3af0283210c39463cHash the line above with SHA-256 to reproduce the fingerprint. It proves the record is unchanged since import. It is not a blockchain entry, and it cannot prove the source data is accurate.