FY2026 GAA: ₱6.79T
PisoScan

Project 16KL0019

DPWH infrastructure contract
Contract ID:
16KL0019
Fingerprint:
e1516948c6f023…162ee5dea8 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 26, 2016 (10 yrs 8 mo ago) · Target/actual end May 25, 2016
Description:
MULTI-PURPOSE BUILDING (CONSTRUCTION OF COVERED COURT), BRGY.LOGUILO, ALUBIJID,MISAMIS ORIENTAL
Category:
Buildings and Facilities
Implementing office:
Contractor:
CAGALAWAN ENTERPRISES · DPWH contractor code 38019
Contract amount:
₱1,980,000.00 (₱2.0M)
Funding source:
Regular Infra - GAA 2016 Locally Funded Projects
Budget year:
2016

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
1df775612082…Feb 18, 2016DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - MISAMIS ORIENTAL 2₱1,861,302.36

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25K00223Jul 2, 2025CONSTRUCTION OF CONRETE BRIDGE-MAT-I - LUBILAN, NAAWAN TO MISAMIS ORIENTAL WEST DIVERSION ROAD, (OPOL TO LUGAIT), PACKAGE 10, MISAMIS ORIENTALOn-Going₱238.2M
25K00389Jul 2, 2025CONSTRUCTION OF CONCRETE ROAD-MAT-I - LUBILAN, NAAWAN TO MISAMIS ORIENTAL WEST DIVERSION ROAD, (OPOL TO LUGAIT), PACKAGE 9, MISAMIS ORIENTALOn-Going₱238.3M
25K00406Jul 2, 2025CONSTRUCTION OF CONRETE ROAD, MAT-I - LUBILAN, NAAWAN TO MISAMIS ORIENTAL WEST DIVERSION ROAD, (OPOL TO LUGAIT), PACKAGE 8, MISAMIS ORIENTALOn-Going₱238.3M
25K00404May 30, 2025CONSTRUCTION OF ROAD LEADING TO TUGASNON HOT SPRINGS (PHASE 2), BARANGAY TUGASNON, ALUBIJID, MISAMIS ORIENTALOn-Going₱115.5M
25KL0099May 28, 2025CONSTRUCTION OF SAMPATULOG INTEGRATED SCHOOL ALUBIJID, MISAMIS ORIENTALOn-Going₱9.8M
25KL0120May 23, 2025CONSTRUCTION OF ROAD AT BRGY. BENIGWAYAN, ALUBIJID, MISAMIS ORIENTALCompleted₱7.4M
25KL0125May 23, 2025REHABILITATION / CONCRETING OF ZONE 4-ZONE 1 ROAD, BARANGAY BARRA, OPOL, MISAMIS ORIENTALOn-Going₱48.5M
25KL0031May 22, 2025CONSTRUCTION OF ROAD, BARANGAY LAGTANG, ALUBIJID, MISAMIS ORIENTALOn-Going₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.