Project 16LD0024
DPWH infrastructure contract
Contract ID:
16LD0024
Fingerprint:
d1ce16de8e0894…d764e35c91 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 6, 2016 (10 yrs 4 mo ago) · Target/actual end Oct 24, 2016
Description:
CONCRETING OF ALTAVISTA FMR, BRGY. ALTAVISTA, BANSALAN, DAVAO DEL SUR
Category:
Roads
Implementing office:
DPWH Davao del Sur DEO · Region XI
Contractor:
TWO DEGREES CONSTRUCTION AND SUPPLY · DPWH contractor code 36734
Contract amount:
₱3,945,418.07 (₱3.9M)
Funding source:
Outside Infra - GAA 2016 DA Farm-to-Market Roads
Budget year:
2016
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 857bbb7335e7… | Jun 13, 2016 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - DAVAO DEL SUR 1ST | ₱3,945,418.07 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25LD0194 | Sep 22, 2025 | PREVENTIVE MAINTENANCE OF ROAD;: ASPHALT OVERLAY- DAVAO- COTABATO ROAD (JCT. DIGOS-COTABATO SECTION)-K1580+625-K1581+434, K1582+118-K1582+670, DAVAO DEL SUR | Completed | ₱96.5M |
| 25LD0170 | Jul 22, 2025 | CONSTRUCTION OF ROAD, BRGY. SIBAYAN, MUNICIPALITY OF BANSALAN, DAVAO DEL SUR | Completed | ₱4.8M |
| 25LD0169 | Jun 25, 2025 | CONSTRUCTION OF CONCRETE REVETMENT/DIKE AT BARANGAY RIZAL, BANSALAN, DAVAO DEL SUR | Completed | ₱99.0M |
| 25LD0186 | Jun 25, 2025 | CONSTRUCTION OF ROAD AT BARANGAY DOLO, BANSALAN, DAVAO DEL SUR | Completed | ₱4.8M |
| 24LD0215 | May 28, 2025 | CONCRETING OF FMR LOCATED AT BARANGAY LINAWAN, BANSALAN, DAVAO DEL SUR | Completed | ₱9.9M |
| 25LD0105 | Mar 24, 2025 | CONSTRUCTION OF SK FEDERATION MPB, PROVINCIAL CAPITOL, MATTI, DIGOS CITY, DAVAO DEL SUR | On-Going | ₱4.8M |
| 25LD0106 | Mar 24, 2025 | CONSTRUCTION OF MPB, BRGY. DOLO, BANSALAN, DAVAO DEL SUR | Completed | ₱4.8M |
| 25LD0123 | Mar 24, 2025 | CONSTRUCTION OF MULTIPURPOSE BUILDING, BRGY. DARAPUAY, BANSALAN, DAVAO DEL SUR | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.