Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 16MC0014

DPWH infrastructure contract
Contract ID:
16MC0014
Fingerprint:
406e1807f86d5b…a1bf1700f2 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 27, 2016 (10 yrs 7 mo ago) · Target/actual end Mar 31, 2017
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) BRGY. KILADA, MATALAM, COTABATO (RE-PUBLISHED)
Category:
Buildings and Facilities
Implementing office:
DPWH Cotabato 2nd DEO · Region XII
Contractor:
NEWCON BUILDERS CONST AND SUPPLY, INC. · DPWH contractor code 38725
As listed: NEWCON BUILDERS CONST. & SUPPLY, INC.
Contract amount:
₱1,885,152.62 (₱1.9M)
Funding source:
Regular Infra - GAA 2016 Locally Funded Projects
Budget year:
2016

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.