Project 16ME0112
DPWH infrastructure contract
Contract ID:
16ME0112
Fingerprint:
faba05f971d011…67eaa147da Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 14, 2016 (10 yrs 4 mo ago) · Target/actual end Dec 15, 2016
Description:
CONST. OF RAIN WATER COLLECTION SYSTEM, ALABEL, AND MALUNGON, SARANGANI.: 1. DATAL CONDE PS; 2. UPPER DOMOLOK ES; 3. TAGAYTAY IS; 4. SPRING IS; 5. DATAL ANGGAS IS, 6. PARAISO ES; 7. SALILUK L. MACANTAL ES; 8. NOP ES, ALL OF ALABEL: 9. PIKONG ES; 10. SAN R
Category:
Water Provision and Storage
Implementing office:
DPWH Sarangani DEO · Region XII
Contractor:
KEVIN YOSHI BUILDERS · DPWH contractor code 32216
As listed: KEVIN YOSHI BUILDERS(FORMERLY:CON BUILDERS)
Contract amount:
₱3,275,395.17 (₱3.3M)
Funding source:
Regular Infra - GAA 2016 MFO-3
Budget year:
2016
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25ME0120 | Sep 19, 2025 | COMPLETION OF SITIO DATAL BACA MULTI-PURPOSE BUILDING, DATAL BATONG, MALUNGON, SARANGANI PROVINCE | Completed | ₱4.9M |
| 25ME0107 | Aug 15, 2025 | CONSTRUCTION (COMPLETION) TAMBAN SOLAR WATER SYSTEM, MALUNGON, SARANGANI PROVINCE | Completed | ₱3.0M |
| 25M00010 | Aug 14, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE -MAHARLIKA HIGHWAY (DIGOS-MAKAR RD) -K1621+450 - K1621+459, MALUNGON, SARANGANI | On-Going | ₱8.0M |
| 25M00009 | Aug 6, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE -MAHARLIKA HIGHWAY (DIGOS-MAKAR RD) -K1603+200 - K1603+229, MALUNGON, SARANGANI | On-Going | ₱30.0M |
| 25LE0039 | Jul 17, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY DATU INTAN, STA. MARIA, DAVAO OCCIDENTAL | On-Going | ₱4.9M |
| 25ME0079 | Jul 15, 2025 | REHABILITATION OF MALUNGON MUNICIPAL GYMNASIUM, POBLACION, MALUNGON, SARANGANI PROVINCE | On-Going | ₱40.6M |
| 25M00013 | Jul 4, 2025 | ROAD WIDENING - MAHARLIKA HIGHWAY (DIGOS-MAKAR RD) - K1612+961 - K1613+532, K1613+590 - K1613+996, K1620+098 - K1620+322 MALUNGON, SARANGANI | On-Going | ₱47.3M |
| 25ME0061 | May 30, 2025 | CONSTRUCTION OF BUAYAN RIS, PROPOSED 800M PROTECTION WORKS AT DOWNSTREAM AND UPSTREAM OF NIA DIVERSION WORKS (300M BOTH SIDES D/S AND 200M BOTH SIDES U/S, MALUNGON, SARANGANI PROVINCE | Completed | ₱14.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.