Project 16ME0142
DPWH infrastructure contract
Contract ID:
16ME0142
Fingerprint:
d4571d86cad443…34cfe347bd Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Nov 30, 2016 (9 yrs 11 mo ago) · Target/actual end May 30, 2017
Description:
CONST. OF KIHAN BHS, MALAPATAN, SARANGANI PROVINCE
Category:
Buildings and Facilities
Implementing office:
DPWH Sarangani DEO · Region XII
Contractor:
YAP MABUHAY ENTERPRISES INCORPORATED · DPWH contractor code 15540
Contract amount:
₱1,687,274.58 (₱1.7M)
Funding source:
Outside Infra - GAA 2016 DOH HFEP
Budget year:
2016
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25ME0116 | Sep 23, 2025 | REHABILITATION OF SEA WALL, PUROK 8, BARANGAY POBLACION, MALAPATAN, SARANGANI PROVINCE | On-Going | ₱59.4M |
| 25ME0122 | Sep 23, 2025 | CONSTRUCTION OF PUROK MAGUINDANAO MULTI-PURPOSE BUILDING, LUN PADIDU, MALAPATAN, SARANGANI PROVINCE | Completed | ₱4.9M |
| 25ME0121 | Sep 19, 2025 | COMPLETION OF LUN MASLA MULTI-PURPOSE BUILDING (CONSTRUCTION OF BENCHES), LUN MASLA, MALAPATAN, SARANGANI PROVINCE | Completed | ₱4.9M |
| 25ME0115 | Aug 15, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, (MALAPATAN COLLEGE OF SCIENCE AND TECHNOLOGY), MALAPATAN, SARANGANI PROVINCE | Completed | ₱49.5M |
| 25ME0101 | Aug 7, 2025 | CONSTRUCTION OF TUYAN MULTI-PURPOSE BUILDING, TUYAN, MALAPATAN, SARANGANI PROVINCE | Completed | ₱5.9M |
| 25ME0102 | Aug 7, 2025 | CONSTRUCTION OF SAPU MASLA MULTI-PURPOSE BUILDING (BARANGAY HALL), SAPU MASLA, MALAPATAN, SARANGANI PROVINCE | Completed | ₱5.9M |
| 25ME0020 | Jul 30, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG SARANGANI - DAVAO DEL SUR COASTAL RD K1678+940 - K1679+160, MALAPATAN, SARANGANI PROVINCE | Completed | ₱93.5M |
| 25ME0088 | Jul 30, 2025 | CONSTRUCTION OF LIBI MULTI-PURPOSE BUILDING, LIBI, MALAPATAN, SARANGANI PROVINCE | Completed | ₱5.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.