Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 16MF0026

DPWH infrastructure contract
Contract ID:
16MF0026
Fingerprint:
3952a245bf3f3f…506d2f614e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 1, 2016 (10 yrs 5 mo ago) · Target/actual end Sep 29, 2016
Description:
CONST. OF 1-UNIT STANDARD TECHNICAL AND VOCATIONAL BUILDING AT SAN SAN EMMANUEL
Category:
Buildings and Facilities
Implementing office:
Contract amount:
₱2,687,611.75 (₱2.7M)
Funding source:
Outside Infra - GAA 2016 DepED BEFF
Budget year:
2016

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25M00262Aug 11, 2025PREVENTIVE MAINTENANCE - DULAWAN-MARBEL RD - K1768 + 571 - K1769 + 071, TACURONG, SULTAN KUDARATOn-Going₱46.8M
25MF0036Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. RAJAH MUDA, TACURONG, SULTAN KUDARATCompleted₱4.8M
25MF0037Jul 28, 2025CONSTRUCTION OF RIVERWALL PROTECTION PROJECTS IN BRGY. RAJAH NUDA AND BRGY. PARAS, TACURONG, SULTAN KUDARATCompleted₱4.8M
25MF0003Mar 26, 2025PREVENTIVE MAINTENANCE OF ROAD:ASPHALT OVERLAY - DULAWAN - MARBEL RD - K1764 + (-526) - K1764 + 344Completed₱98.4M
25MF0004Mar 26, 2025PREVENTIVE MAINTENANCE OF ROAD:ASPHALT OVERLAY - DULAWAN - MARBEL RD - K1762 + 433 - K1763 + 418Completed₱110.0M
25MF0005Mar 26, 2025CONSTRUCTION OF DRAINAGE STRUCTURE ALONG ROAD - KIDAPAWAN - ALLAH JUNCTION ROAD K1674 + 056 - K1674 + 719Completed₱20.8M
25MF0007Mar 26, 2025ROAD WIDENING - DULAWAN - MARBEL ROAD - K1758 + 524 - K1760 + 404On-Going₱53.4M
25MF0008Mar 26, 2025ROAD WIDENING - DULAWAN - MARBEL RD - K1766 + 064 - K1766 + 640Completed₱17.1M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.