Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 16NB0008

DPWH infrastructure contract
Contract ID:
16NB0008
Fingerprint:
6ec34c9c26d656…70ec7e5744 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 28, 2016 (10 yrs 2 mo ago) · Target/actual end Sep 30, 2016
Description:
CONST. OF RAINWATER COLLECTION SYSTEM(RWCS), UNDER AGUSAN DEL SUR 1ST DEO
Category:
Water Provision and Storage
Implementing office:
Contractor:
ABADA CONSTRUCTION AND SUPPLY · DPWH contractor code 37005
Contract amount:
₱3,182,225.79 (₱3.2M)
Funding source:
Regular Infra - GAA 2016 MFO-3
Budget year:
2016

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
82ce4ec0f3f1…Aug 4, 2016DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AGUSAN DEL SUR 1ST₱3,182,225.79

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.