Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 16OD0083

DPWH infrastructure contract
Contract ID:
16OD0083
Fingerprint:
1959aea9273d10…26c472eec6 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Nov 28, 2016 (9 yrs 11 mo ago) · Target/actual end Apr 14, 2019
Description:
CONSTRUCTION OF 4-STOREY 12-CLASSROOM SCHOOL BUILDING TALA HS, CALOOCAN CITY
Category:
Buildings and Facilities
Implementing office:
DPWH Metro Manila 3rd DEO · National Capital Region
Contractor:
AYLAN CONSTRUCTION AND TRADING · DPWH contractor code 11884
As listed: AYLAN CONSTRUCTION & TRADING
Contract amount:
₱21,660,889.92 (₱21.7M)
Funding source:
Outside Infra - GAA 2016 DepED BEFF
Budget year:
2016

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
531ccdfbd344…Nov 11, 2016DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - METRO MANILA 3RD E₱21,660,889.92

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25OD0370Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, NORTH OLYMPUS, BARANGAY 172, CALOOCAN CITYOn-Going₱9.2M
25OD0371Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 156, CALOOCAN CITYOn-Going₱10.5M
25OD0373Jul 28, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), CELINA HOMES, BARANGAY 168, CALOOCAN CITYOn-Going₱4.8M
25OD0374Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), PHASE 2, BARANGAY 171, CALOOCAN CITYCompleted₱4.8M
25OD0375Jul 28, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (SPORTS COMPLEX), BARANGAY 176, CALOOCAN CITY (PHASE 3)On-Going₱23.9M
25OD0376Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. 180, CALOOCAN CITYOn-Going₱28.6M
25OD0368Jul 21, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY 153, CALOOCAN CITYOn-Going₱28.7M
25OD0360Jul 9, 2025CONSTRUCTION (COMPLETION) PUP NORTH CALOOCAN CITY CAMPUS ACADEMIC BUILDING INCLUDING GROUND IMPROVEMENT (PHASE 6), BRGY. 168, CALOOCAN CITYOn-Going₱139.3M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.