Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 16OH0081

DPWH infrastructure contract
Contract ID:
16OH0081
Fingerprint:
d392977c40bcee…7a0e5d9565 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jan 24, 2017 (9 yrs 9 mo ago) · Target/actual end May 23, 2017
Description:
RAINWATER COLLECTOR SYSTEM @1.P.QUIRINOH/S, BACOOD ST. STA. MESA 2. BACOOD E/S, MAG-ALBERT ST, STA.M
Category:
Water Provision and Storage
Implementing office:
DPWH South Manila DEO · National Capital Region
Contractor:
MCB ZAMORA CONSTRUCTION & SUPPLY · DPWH contractor code 32006
Location:
Not stated in the source
Contract amount:
₱3,202,103.54 (₱3.2M)
Funding source:
Regular Infra - GAA 2016 MFO-3
Budget year:
2016

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
98ce89a83f5f…Oct 18, 2016DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SOUTH METRO MANILA₱3,202,103.54

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.