Project 16PA0020
DPWH infrastructure contract
Contract ID:
16PA0020
Fingerprint:
c02d114644e116…a72522eedf Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 3, 2016 (10 yrs 3 mo ago) · Target/actual end Dec 6, 2016
Description:
CONSTRUCTION OF 2-STOREY, 4-CLASSROOM SCHOOL BUILDING
Category:
Buildings and Facilities
Implementing office:
DPWH Abra DEO · Cordillera Administrative Region
Contractor:
WERR CORPORATION INTERNATIONAL · DPWH contractor code 14133
Contract amount:
₱6,467,086.00 (₱6.5M)
Funding source:
Outside Infra - GAA 2016 DepED BEFF, Outside Infra - GAA 2017 DepEd BEFF
Budget year:
2017
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 974b8e68abf5… | May 20, 2016 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ABRA ED | ₱6,467,086.00 |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.