Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 16PA0077

DPWH infrastructure contract
Contract ID:
16PA0077
Fingerprint:
d9e65dba6b9fdc…15f1db42db Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 14, 2017 (9 yrs 9 mo ago) · Target/actual end Sep 1, 2017
Description:
16PA0077 - ASSET PRESERVATION OF NATIONAL ROADS - REHABILITATION/RECONSTRUCTION/UPGRADING OF ABRA-ILOCOS SUR ROAD; KO398+000 - KO398+475; KO398+513 - KO399+000
Category:
Roads
Implementing office:
DPWH Abra DEO · Cordillera Administrative Region
Contractor:
R.S. SEPIAN CONSTRUCTION & TRUCKING · DPWH contractor code 20519
Contract amount:
₱27,404,701.08 (₱27.4M)
Funding source:
Regular Infra - GAA 2017 MFO-1
Budget year:
2017

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
d8990be8b554…Jan 6, 2017DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ABRA ED₱25,633,386.33

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25PA0022Mar 26, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), SUYO PILOT ELEMENTARY SCHOOL, BARANGAY PAMUTIC, PIDIGAN, ABRAOn-Going₱2.4M
25PA0015Mar 19, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY ARAB, PIDIGAN, ABRAOn-Going₱4.8M
24PA0217Jan 15, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY SUYO, PIDIGAN, ABRAOn-Going₱4.8M
24PA0218Jan 15, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY POBLACION EAST, PIDIGAN, ABRAOn-Going₱4.7M
24PA0035Jul 24, 2024REPLACEMENT OF PERMANENT WEAK BRIDGES-ALINAYA BRIDGE (B02224LZ) ALONG ABRA-ILOCOS SUR ROAD, PIDIGAN, ABRAOn-Going₱57.8M
24PA0103Apr 15, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY PAMUTIC, PIDIGAN, ABRAOn-Going₱4.8M
24PA0104Apr 15, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY YUYENG, PIDIGAN, ABRACompleted₱4.9M
24PA0070Feb 26, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY IMMULI, PIDIGAN, ABRACompleted₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.