Project 17AD0045
DPWH infrastructure contract
Contract ID:
17AD0045
Fingerprint:
37a4b2bc23dce6…5453bd9ada Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 18, 2017 (9 yrs 5 mo ago) · Target/actual end Sep 30, 2017
Description:
COMPLETION OF RHU BUILDING, BURGOS RHU, BURGOS, ILOCOS SUR
Category:
Buildings and Facilities
Implementing office:
DPWH Ilocos Sur 2nd DEO · Region I
Contractor:
MBB CONSTRUCTION & SUPPLY · DPWH contractor code 11363
As listed: MBB CONSTRUCTION AND SUPPLY (FORMERLY: MBB CONSTRUCTION)
Contract amount:
₱2,385,933.29 (₱2.4M)
Funding source:
Outside Infra - GAA 2016 DOH HFEP
Budget year:
2016
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 1c81ab72f56e… | May 4, 2017 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOCOS SUR 2ND DEO | ₱2,385,933.29 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25AD0061 | May 22, 2025 | SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BURGOS, ILOCOS SUR | On-Going | ₱48.2M |
| 25AD0008 | Mar 19, 2025 | REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - BURGOS-LIDLIDDA RD - (S00154LZ) CHAINAGE 075 - CHAINAGE 400 | Completed | ₱5.8M |
| 25AD0049 | Mar 19, 2025 | CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD PROTECTION WORKS AT STA. MARIA-BURGOS NIS, BURGOS, ILOCOS SUR | Completed | ₱14.3M |
| 25AD0034 | Feb 10, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BURGOS, ILOCOS SUR | Completed | ₱9.6M |
| 24AD0092 | Jun 4, 2024 | CONSTRUCTION OF BRGY. MANABOC FMR, BRGY. MANABOC, BURGOS, ILOCOS SUR | Completed | ₱14.9M |
| 24A00449 | May 3, 2024 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES, BURGOS BRIDGE, BURGOS, ILOCOS SUR | Completed | ₱19.3M |
| 24AD0052 | Apr 12, 2024 | FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF LUNA RIVER CONTROL, BURGOS, ILOCOS SUR | Completed | ₱19.2M |
| 24AD0047 | Mar 27, 2024 | FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS FACILITIES - CONSTRUCTION OF BURGOS FLOOD CONTROL, BURGOS, ILOCOS SUR | Completed | ₱14.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.