Project 17AE0038
DPWH infrastructure contract
Contract ID:
17AE0038
Fingerprint:
be64e483ae835c…562add4ed0 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 15, 2017 (9 yrs 8 mo ago) · Target/actual end Feb 11, 2018
Description:
CONSTRUCTION OF DRAINAGE ALONG MANILA NORTH ROAD, K0298+808 TO K0299+960, K0311+000 TO K0311+926
Category:
Roads
Implementing office:
DPWH La Union 1st DEO · Region I
Contractor:
Contract amount:
₱34,299,640.95 (₱34.3M)
Funding source:
Regular Infra - GAA 2017 MFO-1
Budget year:
2017
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 06c62023ca0b… | Feb 13, 2017 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LA UNION 1ST ED | ₱32,803,270.68 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25AE0005 | Mar 20, 2025 | CONSTRUCTION OF NEW BRIDGES - SAN PABLO BR. ALONG MANILA NORTH RD. | Completed | ₱28.3M |
| 25A00026 | Feb 24, 2025 | RETROFITTING / STRENGTHENING OF PERMANENT BRIDGES, PANTAR BR. (B02656LZ) ALONG MANILA NORTH ROAD | Completed | ₱5.2M |
| 25A00028 | Feb 24, 2025 | RETROFITTING / STRENGTHENING OF PERMANENT BRIDGES, MASUPE BR. (B04861LZ) ALONG MANILA NORTH ROAD | Completed | ₱2.9M |
| 25AE0020 | Feb 17, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (FIRE STATION), BARANGAY POBLACION, BALAOAN, LA UNION | Completed | ₱6.8M |
| 25AE0032 | Feb 17, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY (RURAL HEALTH UNIT), BARANGAY BUTUBUT OESTE, BALAOAN, LA UNION | Completed | ₱11.6M |
| 24AE0073 | Jul 26, 2024 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - CONSTRUCTION OF ROAD, BARANGAY NAGSABARAN, BALAOAN, LA UNION | Completed | ₱21.6M |
| 24AE0010 | May 15, 2024 | CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - TERTIARY ROADS - BACNOTAN - LUNA - BALAOAN RD - K0292+500 - K0292+700 | Completed | ₱26.9M |
| 24A00487 | May 3, 2024 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MALUYO RIVER, BARANGAY SABLUT, BALAOAN, LA UNION | Completed | ₱96.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.