DPWH infrastructure contract
Contract ID:
17AH0039
Fingerprint:
5900fc731d96af…ab8fa19e0a Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 8, 2017 (9 yrs 8 mo ago) · Target/actual end Aug 20, 2017
Description:
REHAB/MAJOR REPAIR OF PERMANENT BR AT TATAG BR (B02138LZ) ALONG PANG-ZAMB RD, LABRADOR, PANG
Category:
Bridges
Implementing office:
Contractor:
JHI CONSTRUCTION & SUPPLY · DPWH contractor code 19317
Contract amount:
₱8,099,700.00 (₱8.1M)
Funding source:
Regular Infra - GAA 2017 MFO-1
Budget year:
2017

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
43d5a10bfd8d…Feb 20, 2017DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PANGASINAN 2ND₱8,099,700.00

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25AH0158Jun 11, 2025CONSTRUCTION OF MULTI-PURPOSED BUILDING,PHASE 2,BRGY. LAOIS,LABRADOR, PANGASINANOn-Going₱4.8M
25A00491May 27, 2025BASIC INFRASTRUCTURE PROGRAM (BIP) - CLUSTER I, CONSTRUCTION OF MULTI - PURPOSE BUILDING (1. BRGY LASIP, LINGAYEN, PANGASINAN; 2. BRGY LAOIS, LABRADOR, PANGASINAN;3. BRGY BASING, BINMALEY, PANGASINAN)On-Going₱29.0M
25AH0078Mar 20, 2025REHAB/RECONST'N./UPGRADING OF DAMAGED PAVED ROADS-PANG.-ZAMBALES RD.-K0341+(-840)-K0341+478,K0341+53On-Going₱18.4M
25AH0079Mar 20, 2025REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PANG.-ZAMBALES RD.-K0341+750-K0342+32On-Going₱6.4M
25AH0083Mar 17, 2025WIDENING OF PERMANENT BRIDGES AT BONGALON BR.(B02137LZ)ALONG PANGASINAN-ZAMBALES RD.(PHASE III),LABROn-Going₱27.5M
25AH0095Mar 17, 2025INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES(ROADWAY LIGHTING)ALONG LINGAYEN-LABRADOR DIV.RD.-Completed₱43.7M
25AH0087Feb 24, 2025CONSTRUCTION OF EMBANKMENT PROTECTION AT BOLO CIS,LABRADOR, PANGASINANOn-Going₱14.4M
25AH0099Feb 24, 2025CONSTRUCTION (COMPLETION)OF MULTI-PURPOSE BUILDING(BARANGAY HALL)BRGY. SAN GONZALO,LABRADOR, PANGASICompleted₱2.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.