Completed
Physical progress:
100%
Timeline:
Start Apr 18, 2017 (9 yrs 7 mo ago) · Target/actual end Jul 11, 2017
Description:
CONSTN OF ONE STRY TWO CL SB W/ TOILET ATTACHED AT SAN PABLO E/S, UMINGAN, PANGASINAN
Category:
Buildings and Facilities
Implementing office:
DPWH Pangasinan 3rd DEO · Region I
Contractor:
MKM MARKETING · DPWH contractor code 15586
Contract amount:
₱1,861,615.52 (₱1.9M)
Funding source:
Outside Infra - GAA 2016 DepED BEFF
Budget year:
2016
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| d5327b85034a… | Mar 31, 2017 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PANGASINAN 3RD DEO | ₱1,861,615.52 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25AI0187 | Jul 18, 2025 | REHABILITATION OF ROAD, PHASE 1, UMINGAN, PANGASINAN | On-Going | ₱117.0M |
| 25AI0188 | Jul 18, 2025 | REHABILITATION OF ROAD, PHASE 2, UMINGAN, PANGASINAN | On-Going | ₱117.0M |
| 25A00478 | Jul 4, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION / REHABILITATION OF ROADS, UMINGAN, PANGASINAN, PHASE 3 | On-Going | ₱16.3M |
| 25AI0203 | May 29, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BANILA AND ALLIED RIVERS, UMINGAN, PANGASINAN (PACKAGE 3) | Completed | ₱48.7M |
| 25AI0204 | May 29, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BANILA AND ALLIED RIVERS, UMINGAN, PANGASINAN (PACKAGE 4) | Completed | ₱48.7M |
| 25AI0205 | May 29, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BANILA AND ALLIED RIVERS, UMINGAN, PANGASINAN (PACKAGE 5) | Completed | ₱48.7M |
| 25AI0206 | May 29, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BANILA AND ALLIED RIVERS, UMINGAN, PANGASINAN (PACKAGE 6) | Completed | ₱48.7M |
| 25A00268 | Apr 7, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF ROAD, TAYUG, PANGASINAN | On-Going | ₱19.2M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.