Project 17AI0503
DPWH infrastructure contract
Contract ID:
17AI0503
Fingerprint:
6ea73d6d834424…f217507375 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 20, 2017 (8 yrs 10 mo ago) · Target/actual end Jul 27, 2018
Description:
CONSTN OF TWO STRY FOUR CL SB AT SAN JOSE E/S, NATIVIDAD, PANGASINAN
Category:
Buildings and Facilities
Implementing office:
DPWH Pangasinan 3rd DEO · Region I
Contractor:
PHESCO, INCORPORATED · DPWH contractor code 145
Contract amount:
₱9,556,523.46 (₱9.6M)
Funding source:
Outside Infra - GAA 2017 DepEd BEFF
Budget year:
2017
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 381f45512059… | Dec 18, 2017 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PANGASINAN 3RD DEO | ₱9,556,523.46 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25AI0175 | May 27, 2025 | CONSTRUCTION OF ROAD, SITIO SAN JOSE - CACANDONGAN, NATIVIDAD, PANGASINAN | On-Going | ₱9.6M |
| 25AI0062 | Mar 13, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CABULANDAYAN RIVER, NATIVIDAD, PANGASINAN (PACKAGE 1) | On-Going | ₱95.2M |
| 25AI0063 | Mar 13, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CABULANDAYAN RIVER, NATIVIDAD, PANGASINAN (PACKAGE 2) | On-Going | ₱95.2M |
| 25AI0064 | Mar 13, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CABULANDAYAN RIVER, SAN NICOLAS, PANGASINAN (PACKAGE 1) | On-Going | ₱95.3M |
| 25AI0068 | Mar 13, 2025 | CONSTRUCTION OF FLOOD CONTROL ALONG CABULANDAYAN RIVERS, SAN NICOLAS, PANGASINAN (PACKAGE 2) | On-Going | ₱47.7M |
| 25A00047 | Feb 24, 2025 | RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES, NINING BR. 1(B00839LZ) ALONG SN NICOLAS-NATIVIDAD-SN QUINTIN-UMINGAN-GUIMBA RD | Completed | ₱11.8M |
| 25A00062 | Feb 24, 2025 | RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES, VIRAY BR.(B00844LZ) ALONG SN NICOLAS-NATIVIDAD-SN QUINTIN-UMINGAN-GUIMBA RD | On-Going | ₱77.2M |
| 25A00075 | Feb 24, 2025 | RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES - PRIMICIAS BR. 3(B01948LZ) ALONG SN NICOLAS-NATIVIDAD-SN QUINTIN-UMINGAN-GUIMBA RD | Completed | ₱4.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.