Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 17BE0014

DPWH infrastructure contract
Contract ID:
17BE0014
Fingerprint:
bc74e50fa10eb3…cfdaf747b9 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 20, 2017 (9 yrs 7 mo ago) · Target/actual end Jul 7, 2017
Description:
CONCRETING OF SANTOR-ANDARAYAN BARANGAY ROAD DELFIN ALBANO, ISABELA
Category:
Roads
Implementing office:
Contractor:
ABE GENERAL CONTRACTOR · DPWH contractor code 33982
Contract amount:
₱9,404,162.90 (₱9.4M)
Funding source:
Regular Infra - GAA 2017 LFP
Budget year:
2017

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
9b19ff9966b0…Mar 2, 2017DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ISABELA 1ST DEO₱9,404,178.21

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.