Project 17BE0028
DPWH infrastructure contract
Contract ID:
17BE0028
Fingerprint:
c627711778c7d0…0152743542 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 27, 2017 (9 yrs 7 mo ago) · Target/actual end Aug 23, 2017
Description:
CONCRETING OF BAGUTAN-CANOGAN ABAJO SUR-ABAJO NORTE ROAD STO. TOMAS, ISABELA
Category:
Roads
Implementing office:
DPWH Isabela 1st DEO · Region II
Contractor:
BMJ CONSTRUCTION · DPWH contractor code 14571
Contract amount:
₱18,809,354.04 (₱18.8M)
Funding source:
Regular Infra - GAA 2017 LFP
Budget year:
2017
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 497ec8d7b7ae… | Mar 9, 2017 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ISABELA 1ST DEO | ₱18,809,363.35 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25BE0168 | Jun 17, 2026 | CONSTRUCTION OF CLASSROOMS, CANDANUM INTEGRATED SCHOOL, CABAGAN, ISABELA | On-Going | ₱28.5M |
| 25BE0143 | Jan 22, 2026 | CONCRETING OF SITIO PELO, BRGY. CANSAN FMR, BRGY. CANSAN, CABAGAN, ISABELA | On-Going | ₱14.5M |
| 25BE0131 | Sep 16, 2025 | CONSTRUCTION OF SCHOOL BUILDING, CUBAG INTEGRATED SCHOOL, BARANGAY CUBAG, CABAGAN, ISABELA | Completed | ₱19.3M |
| 24BE0183 | Aug 20, 2025 | CONSTRUCTION OF SEWAGE TREATMENT PLANT, MILAGROS ALBANO DISTRICT HOSPITAL, CABAGAN, ISABELA BARANGAY NGARAG, CABAGAN, ISABELA | On-Going | ₱28.1M |
| 25BE0078 | Jul 14, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD, BARANGAY AGGUB, CABAGAN, ISABELA | On-Going | ₱9.6M |
| 25BE0082 | Jul 14, 2025 | CONCRETING OF MALASI-SAN ANTONIO FMR, BRGY. SITIO MALASI, BRGY. SAN ANTONIO, CABAGAN, ISABELA | On-Going | ₱14.5M |
| 25BE0089 | Jul 14, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR / STRATEGIC PUBLIC BUILDINGS / FACILITIES - CONSTRUCTION OF SLOPE PROTECTION WORKS ALONG CAGAYAN | On-Going | ₱140.3M |
| 25BE0090 | Jul 14, 2025 | ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF SLOPE PROTECTION STRUCTUR | On-Going | ₱93.6M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.