Project 17BF0046
DPWH infrastructure contract
Contract ID:
17BF0046
Fingerprint:
7c8bf2983d72fa…92c084e8c8 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 17, 2017 (9 yrs 7 mo ago) · Target/actual end Jul 12, 2017
Description:
CONSTRUCTION OF BARANGAY ALUNAN COMMUNITY CENTER (COMPLETION), ALUNAN, QUEZON, ISABELA
Category:
Buildings and Facilities
Implementing office:
DPWH Isabela 2nd DEO · Region II
Contractor:
A. DE GUIA CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY: A. DE GUIA CONSTRUCTION) · DPWH contractor code 18228
Contract amount:
₱949,821.08 (₱949.8K)
Funding source:
Regular Infra - GAA 2017 LFP
Budget year:
2017
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26BF0037 | Aug 3, 2026 | ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - LAGUINDAY PARALLEL BR. ALONG SANTIAGO-TUGUEGARAO RD, RIZAL KALINGA | On-Going | ₱56.1M |
| 25BF0104 | Oct 13, 2025 | RAINWATER COLLECTOR SYSTEM 1. VICTORIA ELEMENTARY SCHOOL, AURORA, ISABELA 2. BURGOS NATIONAL HIGH SCHOOL, BURGOS, ISABELA 3. HARANA ELEMENTARY SCHOOL, LUNA, ISABELA 4. BIMONTON INTEGRATED SCHOOL, MALLIG, ISABELA 5. MANANO ELEMENTARY SCHOOL MAIN, MALLIG, | On-Going | ₱2.5M |
| 25BF0068 | Aug 6, 2025 | OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, UPPER CHICO RIVER IRRIGATION SYSTEM, QUEZON, ISABELA | Completed | ₱14.0M |
| 25BF0089 | Aug 4, 2025 | CONSTRUCTION OF SCHOOL BUILDING, MINAGBAG INTEGRATED SCHOOL, QUEZON, ISABELA | Completed | ₱4.8M |
| 25BF0076 | Jul 9, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SAN JUAN, QUEZON, ISABELA | Completed | ₱5.8M |
| 25BF0078 | Jul 9, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (LEGISLATIVE BUILDING), BRGY. SAMONTE, QUEZON, ISABELA | Completed | ₱9.6M |
| 25BF0049 | Jun 30, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY TUROD, QUEZON, ISABELA | On-Going | ₱4.8M |
| 25BF0029 | Jun 16, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (LEGISLATIVE BUILDING), BARANGAY SAMONTE, QUEZON, ISABELA | On-Going | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.