Project 17BF0047
DPWH infrastructure contract
Contract ID:
17BF0047
Fingerprint:
40171d89bd93c0…16d30f04e3 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 3, 2017 (9 yrs 7 mo ago) · Target/actual end Jun 13, 2017
Description:
CONSTRUCTION OF BARANGAY BANNAGAO COMMUNITY CENTER-BLEACHER (COMPLETION), BANNAGAO, AURORA, ISABELA
Category:
Buildings and Facilities
Implementing office:
DPWH Isabela 2nd DEO · Region II
Contractor:
CAMBERWELL CONSTRUCTION AND SUPPLIES · DPWH contractor code 39624
Contract amount:
₱949,724.51 (₱949.7K)
Funding source:
Regular Infra - GAA 2017 LFP
Budget year:
2017
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 2bc91420f47e… | Mar 16, 2017 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ISABELA 2ND DEO | ₱949,724.51 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25BF0112 | Feb 2, 2026 | BASIC EDUCATIONAL FACILITIES FUND (BEFF) (BATCH 1) PRIORITY SCHOOL FACILITIES AND NEW CONSTRUCTION OF CLASSROOMS: CONSTRUCTION OF SCHOOL HEALTH FACILITIES, AURORA CENTRAL SCHOOL, AURORA, ISABELA | Completed | ₱850.6K |
| 25BF0117 | Feb 2, 2026 | BASIC EDUCATIONAL FACILITIES FUND (BEFF) (BATCH 1) PRIORITY SCHOOL FACILITIES AND NEW CONSTRUCTION OF CLASSROOMS, VICTORIA ELEMENTARY SCHOOL, AURORA, ISABELA | Completed | ₱4.8M |
| 25BF0100 | Oct 13, 2025 | OO1: NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - SANTIAGO-TUGUEGARAO ROAD - K0366 + 735.70 - K0367 + 578.70, K0367 + 799 - K0369 + 000, AURORA, ISABELA | On-Going | ₱93.6M |
| 25BF0106 | Oct 13, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY RIZALINA, AURORA, ISABELA | Completed | ₱24.0M |
| 25BF0098 | Sep 1, 2025 | CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING, BRGY. SAN RAFAEL, AURORA, ISABELA | On-Going | ₱4.8M |
| 25BF0075 | Jul 9, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY DALIG - KALINGA, AURORA, ISABELA | Completed | ₱4.8M |
| 25BF0080 | Jul 9, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. MALASIN, AURORA, ISABELA | Completed | ₱4.8M |
| 25BF0081 | Jul 9, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. STA. ROSA, AURORA, ISABELA | On-Going | ₱4.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.