Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 17CC0064

DPWH infrastructure contract
Contract ID:
17CC0064
Fingerprint:
4502355a23ba88…e471c03ee5 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 13, 2017 (9 yrs 3 mo ago) · Target/actual end Feb 8, 2018
Description:
CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BOCAUE RIVER IGULOT-BUNDUCAN-BINANG SECTION BOCAUE, BULACAN
Category:
Flood Control and Drainage
Implementing office:
DPWH Bulacan 1st DEO · Region III
Contractor:
M3 KONSTRACT CORPORATION · DPWH contractor code 20201
As listed: M3 KONSTRACT CORPORATION (FORMERLY:MARGARITA CONSTRUCTION)
Contract amount:
₱13,945,004.23 (₱13.9M)
Funding source:
Regular Infra - GAA 2017 MFO-2
Budget year:
2017

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.