FY2026 GAA: ₱6.79T
PisoScan

Project 17CE0187

DPWH infrastructure contract
Contract ID:
17CE0187
Fingerprint:
8fe7b93c416c5b…e61d5703c5 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 30, 2018 (8 yrs 2 mo ago) · Target/actual end Oct 28, 2018
Description:
CONSTRUCTION OF BARANGAY HALL SAN JUAN, LICAB, NUEVA ECIJA
Category:
Buildings and Facilities
Implementing office:
Contractor:
Contract amount:
₱968,808.51 (₱968.8K)
Funding source:
Regular Infra - GAA 2018 LP
Budget year:
2018

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
036f312ebfda…Aug 13, 2018DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - N. ECIJA 1ST DEO₱968,808.51

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CE0295Jun 2, 2025CONSTRUCTION OF ROAD, BARANGAY SAN JOSE, LICAB, NUEVA ECIJACompleted₱4.9M
25CE0235Apr 2, 2025NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LICAB-VICTORIA RD, NUEVA ECIJACompleted₱33.9M
25CE0265Apr 2, 2025CONSTRUCTION OF ROAD, BARANGAY SANTA MARIA, LICAB, NUEVA ECIJACompleted₱4.9M
25CE0105Mar 21, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TALAVERA RIVER, BARANGAY SANTA LUCIA OLD, ZARAGOZA, NUEVA ECIJACompleted₱48.5M
25CE0019Feb 14, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY CAINGIN TABING ILOG, GUIMBA, NUEVA ECIJACompleted₱3.0M
25CE0065Feb 14, 2025REHABILITATION OF ROAD, BARANGAY POBLACION SUR, LICAB, NUEVA ECIJACompleted₱10.7M
25CE0072Feb 14, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LABONG RIVER, BARANGAY SAN JUAN, LICAB, NUEVA ECIJACompleted₱48.5M
24CE0189Jul 3, 2024NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, TALAVERA - LICAB DIVERSION ROAD, NUEVA ECIJACompleted₱19.4M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.