Project 17CF0186
DPWH infrastructure contract
Contract ID:
17CF0186
Fingerprint:
412fd88958da9d…1d7974d035 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 1, 2017 (8 yrs 11 mo ago) · Target/actual end Mar 11, 2018
Description:
CONSTRUCTION OF 1 STY - 1UW BUILDING, HILARIO E. HERMOSA MEM. HS, LAUR, NUEVA ECIJA 3RD LD
Category:
Buildings and Facilities
Implementing office:
DPWH Nueva Ecija 2nd DEO · Region III
Contractor:
PRUDENZIA CONSTRUCTION AND REALTY DEVELOPMENT CORP. · DPWH contractor code 38823
Location:
Contract amount:
₱3,563,370.07 (₱3.6M)
Funding source:
Outside Infra - GAA 2017 DepEd BEFF
Budget year:
2017