Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 17CJ0026

DPWH infrastructure contract
Contract ID:
17CJ0026
Fingerprint:
164da771442737…41df3b6e89 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 13, 2017 (9 yrs 9 mo ago) · Target/actual end Aug 4, 2017
Description:
CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS; CONSTRUCTION OF SLOPE PROTECTION ALONG CAMILING RIVER CONTROL, SURGUI 2ND - SURGUI 1ST SECTION, CAMILING, TARLAC 1ST LD
Category:
Flood Control and Drainage
Implementing office:
DPWH Tarlac DEO · Region III
Contractor:
Contract amount:
₱39,458,975.78 (₱39.5M)
Funding source:
Regular Infra - GAA 2017 MFO-2
Budget year:
2017

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
36e6efb3a194…Jan 25, 2017DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - TARLAC DEO₱39,458,975.78

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.