Project 17CK0032
DPWH infrastructure contract
Contract ID:
17CK0032
Fingerprint:
09af8258f5034b…ab2b959d79 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 14, 2017 (9 yrs 2 mo ago) · Target/actual end Dec 5, 2018
Description:
DIKING WITH SLOPE PROTECTION SACOBIA-BAMBAN RIVER, PAMPANGA AND TARLAC
Category:
Flood Control and Drainage
Implementing office:
DPWH Flood Control Management Cluster · Central Office
Contractor:
11-16 CONSTRUCTION · DPWH contractor code 29646
Contract amount:
₱96,097,777.28 (₱96.1M)
Funding source:
Regular Infra - GAA 2017 MFO-2
Budget year:
2017
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CK0078 | Apr 3, 2025 | REHABILITATION OF ROAD, DAPDAP RESETTLEMENT, BAMBAN, TARLAC | Completed | ₱96.5M |
| 25CK0097 | Apr 3, 2025 | INSTALLATION OF ROAD SAFETY DEVICES, INFORMATION SIGNS AND SOLAR LIGHTING - PRIMARY ROAD ALONG MANILA NORTH ROAD (CAPAS AND BAMBAN SECTION), CAPAS AND BAMBAN, TARLAC | Completed | ₱98.0M |
| 25CK0112 | Apr 3, 2025 | STRENGTHENING OF RIGHT SIDE EXISTING BANK OF SAN PEDRO SECTION ALONG PARUA RIVER, UPSTREAM OF SCTEX BRIDGE, BAMBAN, TARLAC (PART A) | Completed | ₱69.3M |
| 25CK0047 | Mar 25, 2025 | CONSTRUCTION OF ROAD, BARANGAY SAN PEDRO, BAMBAN, TARLAC | Completed | ₱4.9M |
| 25CK0055 | Feb 13, 2025 | CONSTRUCTION OF ROAD, BARANGAY SANTIAGO, CONCEPCION, TARLAC | On-Going | ₱8.7M |
| 24CK0196 | Jan 4, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PARUA RIVER, UPSTREAM OF SCTEX BRIDGE, BANGCU SECTION, BAMBAN, TARLAC | Completed | ₱48.2M |
| 24CK0135 | Apr 27, 2024 | CONSTRUCTION OF 1-STOREY, 2-CLASSROOM WITH TOILET SCHOOL BUILDING IN ANUPUL ELEMENTARY SCHOOL, BARANGAY ANUPUL, BAMBAN, TARLAC | Completed | ₱5.4M |
| 23CK0115 | Mar 23, 2024 | CONCRETING OF ROAD AT BRGY. CUT-CUT II - BRGY. ANUPUL (PHASE I), CAPAS AND BAMBAN, TARLAC | Completed | ₱75.6M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.