Project 17CL0022
DPWH infrastructure contract
Contract ID:
17CL0022
Fingerprint:
283c08e84c20b6…e8a806a9de Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 13, 2017 (9 yrs 8 mo ago) · Target/actual end Aug 20, 2017
Description:
CONSTRUCTION OF SLOPE PROTECTION/ FLOOD CONTROL, GABOR DIKE (UPSTREAM), SAN FELIPE, ZAMBALES
Category:
GAA 2017 MFO-2
Implementing office:
DPWH Zambales 1st DEO · Region III
Contractor:
Location:
Contract amount:
₱23,002,615.07 (₱23.0M)
Funding source:
Regular Infra - GAA 2017 MFO-2
Budget year:
2017
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.