FY2026 GAA: ₱6.79T
PisoScan

Project 17CM0035

DPWH infrastructure contract
Contract ID:
17CM0035
Fingerprint:
d88b43490f4e56…e5b273e539 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 17, 2017 (9 yrs 8 mo ago) · Target/actual end Oct 14, 2017
Description:
CONST/IMPVT. OF ACCESS RD. SUBIC-CAWAG-BALAYBAY RD. SUBIC, ZAMBALES
Category:
Bridges-Rehabilitation-Concrete, Roads: Rehabilitation - PCCP
Implementing office:
DPWH Zambales 2nd DEO · Region III
Contract amount:
₱44,843,224.77 (₱44.8M)
Funding source:
Regular Infra - Bridges-Rehabilitation-Concrete, Roads: Rehabilitation - PCCP
Budget year:
2017