Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 17CN0032

DPWH infrastructure contract
Contract ID:
17CN0032
Fingerprint:
30eea1150125c6…99491ef8eb Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 23, 2017 (9 yrs 8 mo ago) · Target/actual end Oct 8, 2017
Description:
CONSTRUCTION OF DITEKI FLOOD CONTROL, MARIA AURORA, AURORA
Category:
Flood Control and Drainage
Implementing office:
DPWH Aurora DEO · Region III
Contract amount:
₱29,400,000.00 (₱29.4M)
Funding source:
Regular Infra - GAA 2017 MFO-2
Budget year:
2017

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CN0153Aug 27, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, MARIA AURORA, AURORAOn-Going₱49.0M
25C00484Aug 14, 2025ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS, NUEVA ECIJA-AURORA ROAD, PROVINCE OF AURORAOn-Going₱141.9M
25CN0100Jul 4, 2025CONSTRUCTION OF DRAINAGE CANAL, BARANGAY CADAYACAN, MARIA AURORA, AURORACompleted₱15.4M
25CN0160Jul 4, 2025CONTRUCTION OF BAYANIHAN - QUIRINO ROAD, MARIA AURORA, AURORAOn-Going₱48.0M
25CN0066Jun 9, 2025CONSTRUCTION OF WATER SYSTEM, BARANGAY PUNGLO, MARIA AURORA, AURORAOn-Going₱4.8M
25CN0069Jun 9, 2025CONSTRUCTION OF ROAD, BARANGAY 2, MARIA AURORA, AURORAOn-Going₱9.8M
25CN0027May 28, 2025REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, DIMANI BR. (B02824LZ) ALONG NUEVA ECIJA - AURORA RDCompleted₱7.3M
25CN0015May 27, 2025REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS, A. CASTAÑEDA - MA AURORA - SN LUIS RD, K0193 + (-040) - K0193 + (-010), K0205 + 250 - K0205 + 275Completed₱2.3M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.