Project 17CN0061
DPWH infrastructure contract
Contract ID:
17CN0061
Fingerprint:
7f3e4e137597f9…0b45486168 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 6, 2017 (9 yrs 7 mo ago) · Target/actual end Oct 17, 2017
Description:
REPAIR/REHABILITATION OF CONCRETE ROAD, BRGY. POBLACION, DILASAG, AURORA
Category:
Roads
Implementing office:
DPWH Aurora DEO · Region III
Contractor:
CAVACON CORPORATION (FORMERLY CAGAYAN VALLEY CONST · DPWH contractor code 2622
Contract amount:
₱9,900,000.00 (₱9.9M)
Funding source:
Regular Infra - GAA 2017 LFP
Budget year:
2017
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CN0086 | Apr 3, 2025 | CONSTRUCTION OF ROAD, BARANGAY MASAGANA, DILASAG, AURORA | On-Going | ₱18.7M |
| 25CN0146 | Mar 25, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MANGGITAHAN, DILASAG, AURORA | On-Going | ₱5.0M |
| 25CN0041 | Mar 24, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT) BARANGAY DIAGYAN, DILASAG, AURORA | Completed | ₱3.0M |
| 25CN0055 | Mar 24, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), LAWANG WEST ELEMENTARY SCHOOL, BARANGAY LAWANG, DILASAG, AURORA | Completed | ₱6.9M |
| 25CN0108 | Mar 24, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BARANGAY LAWANG, DILASAG, AURORA | On-Going | ₱9.7M |
| 25CN0117 | Mar 24, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) URA ELEMENTARY SCHOOL, BARANGAY URA, DILASAG, AURORA | On-Going | ₱6.9M |
| 25CN0052 | Feb 18, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), DILAGUIDI ELEMENTARY SCHOOL, BARANGAY DILAGUIDI, DILASAG, AURORA | On-Going | ₱6.9M |
| 25CN0054 | Feb 18, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), LAWANG EAST ELEMENTARY SCHOOL, BARANGAY LAWANG, DILASAG, AURORA | Completed | ₱6.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.