Project 17CN0161

DPWH infrastructure contract
Contract ID:
17CN0161
Fingerprint:
b65f5a02287d5c…03e77cc6da Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Nov 10, 2017 (9 yrs ago) · Target/actual end Feb 17, 2018
Description:
CONSTRUCTION OF CLASSROOM (WORKSHOP BUILDING 7M X 18M), DILASAG NATIONAL HIGH SCHOOL, DILASAG, AURORA
Category:
Buildings and Facilities
Implementing office:
DPWH Aurora DEO · Region III
Contractor:
RADIANCE TRADERS & BUILDERS · DPWH contractor code 32891
Contract amount:
₱2,593,526.88 (₱2.6M)
Funding source:
Outside Infra - GAA 2017 DepEd BEFF
Budget year:
2017

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
7fed6de115db…Oct 25, 2017DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AURORA DEO₱2,593,526.88

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CN0086Apr 3, 2025CONSTRUCTION OF ROAD, BARANGAY MASAGANA, DILASAG, AURORAOn-Going₱18.7M
25CN0146Mar 25, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MANGGITAHAN, DILASAG, AURORAOn-Going₱5.0M
25CN0041Mar 24, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT) BARANGAY DIAGYAN, DILASAG, AURORACompleted₱3.0M
25CN0055Mar 24, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), LAWANG WEST ELEMENTARY SCHOOL, BARANGAY LAWANG, DILASAG, AURORACompleted₱6.9M
25CN0108Mar 24, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BARANGAY LAWANG, DILASAG, AURORAOn-Going₱9.7M
25CN0117Mar 24, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) URA ELEMENTARY SCHOOL, BARANGAY URA, DILASAG, AURORAOn-Going₱6.9M
25CN0052Feb 18, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), DILAGUIDI ELEMENTARY SCHOOL, BARANGAY DILAGUIDI, DILASAG, AURORAOn-Going₱6.9M
25CN0054Feb 18, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), LAWANG EAST ELEMENTARY SCHOOL, BARANGAY LAWANG, DILASAG, AURORACompleted₱6.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.