Project 17D00064
DPWH infrastructure contract
Contract ID:
17D00064
Fingerprint:
100f8fe0ea047b…93bfbdbc1f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Nov 28, 2017 (8 yrs 11 mo ago) · Target/actual end Aug 14, 2020
Description:
CONSTRUCTION/REHABILITATION OF ACCESSIBILITY FACILITIES FOR PHYSICALLY CHALLENGED PERSONS OF C-6, RIZAL 1ST L.D., RIZAL PROVINCE
Category:
Buildings and Facilities
Implementing office:
DPWH Region IV-A · Region IV-A
Contractor:
R.A. PAHATI CONST. & SUPPLY, INC · DPWH contractor code 35843
As listed: R.A. PAHATI CONST. & SUPPLY, INC.
Contract amount:
₱19,299,992.99 (₱19.3M)
Funding source:
Regular Infra - GAA 2017 MFO-3
Budget year:
2017
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 4a288d35b3fb… | Nov 6, 2017 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION IV-A | ₱18,223,328.80 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DN0097 | Jun 26, 2025 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - MANILA EAST RD - K0033+276 - K0033+551, RIZAL (FIRST DISTRICT) | On-Going | ₱7.1M |
| 25DN0098 | May 29, 2025 | CONSTRUCTION OF ROAD AT BARANGAY ITHAN TO BARANGAY KALINAWAN, BINANGONAN, RIZAL (FIRST DISTRICT) | On-Going | ₱19.0M |
| 25DN0101 | May 29, 2025 | CONSTRUCTION OF FLOOD STRUCTURE, CREEK, W. CERRERO GOING TO F. CEQUEÑA, BARANGAY MACAMOT, BINANGONAN, RIZAL (FIRST DISTRICT) | Completed | ₱9.5M |
| 25DN0106 | May 29, 2025 | CONSTRUCTION OF BOX CULVERT CONNECTING BARANGAY JANOSA AND BARANGAY KAYTOME BINANGONAN, RIZAL (FIRST DISTRICT) | On-Going | ₱4.9M |
| 25DN0112 | May 29, 2025 | FY 2025 CONVERGENCE AND SPECIAL SUPPORT PROGRAM - RAINWATER COLLECTOR SYSTEM BINANGONAN, RIZAL (FIRST DISTRICT) | On-Going | ₱2.6M |
| 25DN0067 | May 27, 2025 | CONSTRUCTION OF ROAD AT CABLE WAY GOING TO KASINAY, BARANGAY MACAMOT AND BARANGAY DARANGAN, BINANGONAN, RIZAL (FIRST DISTRICT) | Completed | ₱67.5M |
| 25DN0044 | May 26, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SAN JUAN CREEK, BINANGONAN, RIZAL (FIRST DISTRICT) | Completed | ₱19.6M |
| 25DN0056 | May 26, 2025 | CONSTRUCTION OF BREAKWATER, BARANGAY KALINAWAN GOING TO BARANGAY PIPINDAN, BINANGONAN, RIZAL (FIRST DISTRICT) | On-Going | ₱9.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.