Project 17DC0152
DPWH infrastructure contract
Contract ID:
17DC0152
Fingerprint:
032b043263d16f…fdd5643a99 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 4, 2017 (8 yrs 11 mo ago) · Target/actual end Mar 3, 2018
Description:
ASPHALT OVERLAY ALONG DAANG MAHARLIKA LZ, STO. TOMAS, BATANGAS K0061+162.4 TO K0062+175
Category:
Roads
Implementing office:
DPWH Batangas 3rd DEO · Region IV-A
Contractor:
PHILIPPINE CHEMSTEEL INDUSTRIES, INC. · DPWH contractor code 16965
Contract amount:
₱19,999,347.44 (₱20.0M)
Funding source:
Outside Infra - Special Road Support Fund 2017
Budget year:
2017
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| d9f729032a78… | Nov 23, 2017 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BATANGAS 3RD ED | ₱19,000,754.49 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DC0100 | Jun 10, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF BANK/SLOPE PROTECTION ALONG SAN JUAN RIVER AND SAN JUAN BRIDGE ALONG LIP | On-Going | ₱96.5M |
| 25DC0110 | Jun 2, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - ACCESSS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY SAN ISIDRO NORTE, STO. TOMAS, BA | On-Going | ₱4.8M |
| 25DC0157 | Jun 2, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFASTRUCTURE PROGRAM (BIP), BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, REHABILITATION OF ROADS LOCATED AT SAN MIGUEL (TANGKE ROAD) STO. | On-Going | ₱14.5M |
| 25DC0177 | Jun 2, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - EVACUATION CENTERS/QUARANTINE FACILITIES/PUBLIC HEALTH FACILITIES, CONSTRUCTION OF HOSPITAL AT BRGY. SAN MIGUEL, STO. TOMAS, BATANGAS | On-Going | ₱19.3M |
| 25DC0097 | May 29, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP-PUBLIC WATER SUPPLY SYSTEM, REHABILITATION/IMPROVEMENT OF WATER SYSTEM (BARANGAY SAN PABLO WATER COOPERATIVE SYSTEM), BARANGAY SAN PABLO, STO. TOMAS CITY, BATANGAS | On-Going | ₱4.8M |
| 25DC0109 | May 29, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD AT BARANGAY SAN | On-Going | ₱14.3M |
| 25DC0151 | May 29, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF THE NEW CITY HALL OF STO. TOMAS, BATANGAS (PHASE 1) | On-Going | ₱29.0M |
| 25DC0154 | May 29, 2025 | CONVEREGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD AT BARANGAY SAN LUIS, STO. TOMAS CITY, BAT | On-Going | ₱19.3M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.