Project 17DH0042
DPWH infrastructure contract
Contract ID:
17DH0042
Fingerprint:
c20010d0be0b69…01f6fc27c7 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 28, 2017 (9 yrs 7 mo ago) · Target/actual end Oct 9, 2018
Description:
CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, WIDENING OF BRIDGES INCLUDING ROW TO MORE THAN 2 LANES, MAAPON BRIDGE (BO2494LZ) ALONG PAGSANJAN-LUCBAN ROAD, BRGY. SAN PEDRO, LUISIANA, LAGUNA, 4TH LD
Category:
Bridges
Implementing office:
DPWH Laguna 1st DEO · Region IV-A
Contractor:
HEXAMINDZ CORPORATION (FORMERLY:KILUSANG MAGKAIBIG · DPWH contractor code 31666
Contract amount:
₱15,560,427.13 (₱15.6M)
Funding source:
Regular Infra - GAA 2017 MFO-1
Budget year:
2017
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DH0006 | May 15, 2025 | PREVENTIVE MAINTENANCE-SECONDARY ROADS- PAGSANJAN-LUCBAN RD K0107+220-K0107+865, LUISIANA, LAGUNA | Completed | ₱38.4M |
| 25DH0050 | May 15, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SANTO TOMAS, LUISIANA, LAGUNA | Completed | ₱4.8M |
| 24DH0046 | May 7, 2024 | CONSTRUCTION OF MULTI PURPOSE BUILDING, BRGY. SAN BUENAVENTURA, LUISIANA, LAGUNA | Completed | ₱4.8M |
| 24DH0043 | Apr 14, 2024 | PREVENTIVE MAINTENANCE-SECONDARY ROADS-PAGSANJAN-LUCBAN RD-K0112+292 TO K0113+804, LUISIANA, LAGUNA | Completed | ₱96.4M |
| 24D00021 | Feb 28, 2024 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADSLUISIANA - MAUBAN DIVERSION ROAD, LUISIANA SECTION, LAGUNA | On-Going | ₱84.4M |
| 24DH0017 | Feb 20, 2024 | ROAD WIDENING-SECONDARY ROADS PAGSANJAN-LUCBAN RD. K0104+434-K0104+740, LUISIANA, LAGUNA | Completed | ₱19.6M |
| 23D00090 | Sep 4, 2023 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS LUISIANA - MAUBAN DIVERSION ROAD, LUISIANA SECTION, LAGUNA | On-Going | ₱57.9M |
| 23DH0077 | Jul 29, 2023 | OPENING AND CONCRETING OF BRGY. SAN ANTONIO FMR, BRGY. SAN ANTONIO, LUISIANA, LAGUNA | Completed | ₱9.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.